CLIENT: Turlock Irrigation District
IEC provided due diligence review and owner’s engineering services for the 137 MW Tuolumne Wind Project in Washington State. The project incorporates both Siemens 2.3 MW and REpower 2.0 MW turbines, a collector substation, 230kV transmission line, and a 15,000 sq. ft. O&M building. The due diligence effort included reviewing the design and reliability of both turbine platforms, as well as a detailed review of the project contracts, design drawings and specifications. IEC also provided on-site field engineering support for the project to ensure project quality, compliance with regulatory requirements, and to expedite the construction schedule. IEC continues to support this project as an on-going, as needed resource.